1.jpg

main works

Technical assistance for drafting of the specifications for the contract services of the maintenance of the road network in Lanzarote

Tías, Isla de Lanzarote, Spain

  • Contractor: Área de Obras Públicas, Cabildo de Lanzarote
  • Budget of the works: 4.112.149,52 €
  • Year: 2015

Description

Technical assistance for drafting of the specifications for the contract services of the maintenance of the road network in Lanzarote

Elaboration of characterization report in summer period of Cymodocea nodosa meadows (seagrass beds) in the area of influence of the outfall of Butihondo

Pajara, Island ofFuerteventura, Spain

  • Contractor: Laquafuer Aguas y Medioambiente, S.L.
  • Budget of the works: Not applicable
  • Year: 2014

Description

Preparation of report for characterization of Cymodocea nodosa (sebadales) in the area of influence of the outfall Butihondo in summer. The works to be performed were: characterization of the Sebadal of Butihondo with sampling techniques, analysis of the Prairie State, and visual inspection by recording video and taking pictures.

Drafting of Construction Project of Sanitary Sewer System of Bluefields, Nicaragua

Bluefields, Nicaragua

  • Contractor: Asociación Momentánea Consorcio Veolia-TecniTasa
  • Budget of the works: 7.426.289,70 EUR
  • Year: 2014

Description

The contracted work consisted in the definition, and budgeting, of the necessary works for the execution of the sanitary sewer system in the city of Bluefields, in the municipality of Bluefields, Nicaragua, through a system of tubulars of PVC of simple wall using diameters ranging between 100 and 800 mm. The designed works included 20 wastewater impulsion pipes with diameters ranging from 50 mm to 300 mm. The installation of the sewerage network was designed complete. The total lengths of the materials used in the branches are 45.944,50 m and 16.744,60 m in the impulsion pipes.

Drafting of Construction Project of Sanitary Sewer System of Masaya, Nicaragua

Masaya, Nicaragua

  • Contractor: Asociación Momentánea Consorcio Veolia-TecniTasa
  • Budget of the works: 8.850.722,15 EUR
  • Year: 2014

Description

The contracted work consisted in the definition, and budgeting, of the necessary works for the execution of the sanitary sewer system in the city of Masaya, in the municipality of Masaya, Nicaragua, through a system of tubulars of PVC of simple wall using diameters ranging between 100 and 1.200 mm. The designed works included 2 wastewater impulsion pipes with diameters ranging from 300 mm to 500 mm. The installation of the sewerage network was designed complete. The total lengths of the materials used in the branches are 77.004,19 m and 6.290,89 m in the impulsion pipes.